Contact UsHelp/FAQIndexSearch 

Home About Countries Data Evaluation Learning News Projects Publications Research Topics
Search GO   

Home > Tópicos do Dev > Iniciativa de obtenção de energia... > Veja o desenvolvimento... > Uruguai...

Página Principal
Acerca da iniciativa
Financiamento de estudos de pré-viabilidade
Entre à Biblioteca IEGAS para encontrar ferramentas que o ajudem a planejar projetos GAS
Estudos de Pre-viabilidade
Veja o desenvolvimento de outras atividades de projeto que se realizam no mundo
Brasil: Projeto “NovaGerar” para os aterros sanitários de Marambaia e Adrianópolis
Canadá: região onde se localiza o aterro Waterloo
Chile: aterros La Feria, Lo Errazuriz e Lepanto no aterro Santiago e Valparaíso
Latvia: aterros Riga e Liepaja
México, Monterrey
Polônia: aterros Torun, Gkansk-Szadolki, Krakow-Barycz e Legajny-Olsztyn
África do Sul: aterros Durban, Mariannhill, Bisasar Road e La Mercy
Turquia: aterro Kemerburgas, Istambul
Uruguai: projeto piloto no aterro Las Rosas, Maldonado
Descubra o enorme potencial de recurso do GAS
Explore nossa Câmara de compensação e participe nos fóruns de discussão
Una-se à IEGAS
Encontre as respostas às perguntas mais freqüentes FAQs
Contate-nos
Ingles Español Portugues
 
Síntese

The project's primary objective as a short-term measure is to eliminate the emission of 18,962 tons of methane from the municipal landfill of Las Rosas in Maldonado. The project will build a methane recovery system upon the existing waste pile and six landfill cells and produce electricity to be sold to the national grid owned by UTE. The Project supports investments in civil works and equipment (gas capture, 0.8 MW generation plant, monitoring) and technical assistance (engineering planning, project management, training, dissemination, and evaluation).

The installation of the plant is foreseen to be completed by the end of 2004.


Site Information

Start of Landfill (Year): 1997 (1989 as open dump)
Closing of Landfill (Year/year expected): 2018
TotalSite area (hectares): 19
Area Designated for Land Filling (hectares): 19
Estimated site Capacity at Time of Site Closure (Million tons): 0.16
Estimated Capacity of Waste in Place (2003)(Million tons): NA
Annual Waste Disposal Quantity (1000 tons): 52.2
Installed capacity: 0.8 MW

Baixar o informe do estudo de casos (PDF)

 